Generally speaking, commissioning is to ensure that the equipment can operate normally. Test the machine for a period of time with no load, and continue to work if there is no abnormal situation within this certain period of time.
If there is no test link and work directly, then once an abnormal situation occurs, the equipment will be seriously damaged and it may bring certain risks to the operator.

The test time is usually a few minutes, not very long. This will not bring much loss to the project progress, so the test work before the operation of the cable tray forming machine is essential.
Next are the points that need to be paid attention to during the operation of the cable tray:

1. Test and check the balance cylinder action status of the cable tray forming machine and its oil lubrication system oil circuit, joints, etc.
2. The friction force between the slider and the guide rail of the cable tray forming machine is relatively frequent. Necessary adjustment and correction should be made, and the lubrication of the joint part and the pipeline, etc. should be checked for good operation.
3. Regularly lubricate the gear parts of the cable tray forming machine: the gear transmission box and the internal parts are more likely to be damaged due to frequent operation, and the possibility of loosening is more likely.